Bangladesh’s grid operator has opened an investigation into an Oct. 27 transmission failure that disrupted electricity supplies in parts of Dhaka, Chattogram, and Narsingdi for more than six hours.
The Financial Express reported that Power Grid Company Bangladesh (PGCB) formed a committee led by chief engineer Syed Abadullah Haider Ali. It must report within five working days on the cause and measures to prevent another failure.
A fault on the Meghnaghat-Haripur transmission line at 12:43 p.m. triggered further trips, disconnecting about 5,000 megawatts within minutes, according to the company.
Transmission connections were restored by 2:30 p.m., but restarting power plants and restoring distribution took longer.
Affected institutions included the Secretariat, Supreme Court, Dhaka University, and Bangladesh Bank. The company said service had been restored across affected areas after the prolonged disruption.